If you snooze, you lose – prosecuting under the Building Act 2004

The moment a council officer notices something wrong at a building site, the clock begins ticking on a prosecution.

A council gets just six months to prosecute under the Building Act from that moment.  Once you know (or should know) about non-compliant building work, time starts to run for filing charging documents in Court.

Running out of time is one of the most common problems we see when helping councils with the decision to prosecute.

Unfortunately “who knew what and when” is often the beginning of the end for a council wanting to take enforcement action.

Six months is not a lot of time when you think about what needs to be done.  Council officers have to identify the problem, document it clearly, consider other options (like a notice to fix), seek legal advice, consider delegations and prepare charging documents.

Building Act prosecutions can be a minefield without good systems and specialist help.

“When a building inspector is on a building site and thinks “this is bad” … the clock has started.”

When does the clock start ticking?

When a building inspector is on a building site and thinks “this is bad”, that counts as actual knowledge and the clock has started.  If an ordinary person would say “this can’t have been overlooked, how could it have been missed?” that is constructive knowledge and again time has started to run.

Building Control Officers are busy people and wear many hats.  It would be great if prosecutions weren’t necessary but unfortunately, builders continue to cut corners and the public expects councils to clean up the mess.

Appropriate enforcement action can avoid litigation for councils and save a lot of money and anguish.

We have seen it work and we have also seen the consequences of inaction.  Your biggest problem is time but fortunately, it is the easiest one to solve.

Rice Speir tips for dealing with limitation

The key to avoiding limitation issues is to be proactive.  If a building issue concerns you, then you should start thinking about enforcement and speak with your team.

Not every case needs to be prosecuted but they are all subject to the six month limitation period.

“Setting an electronic calendar reminder helps to prevent time slipping away.”

Setting an electronic calendar reminder is a fantastic way to prevent time from slipping away.

Ask questions and speak with colleagues.  The more you talk about serious building issues the easier it will be to stay within the time limit.

There is a fall-back option.  The same time pressure does not apply when issuing a notice to fix.  By doing so, even after six months has expired, you preserve the ability to file a charging document for failing to comply with the notice to fix.

Finally, we enjoy taking phone calls from you with tricky issues and decisions needing to be made under pressure so keep them coming.

Related news

Not above the law: options when faced with a sovereign citizen

As local councils across New Zealand carry out their statutory duties under the Building Act 2004, a growing challenge has emerged in the form of “sovereign citizens.” These individuals typically attempt to deny the legitimacy of government authority and may attempt to frustrate compliance processes—including by refusing entry to property, rejecting compliance action, or disputing…

Natural Hazard Information: what’s changing for LIMs in 2025

Natural hazards are a topical issue, and big changes are on the horizon for how hazard information is communicated in Land Information Memoranda (LIMs). From 1 July 2025, the Local Government Official Information and Meetings Amendment Act 2023 (LGOIMA) will come into force, introducing changes to the LIM provisions that are specifically tailored to the…

Three-day inspection mandate: well intentioned, but is it well thought out?

In a move designed to improve efficiency and reduce delays in construction projects nationwide, the government has announced a significant new requirement for Building Consent Authorities (BCAs).  Intended to commence from late 2025, BCAs will be required to complete 80 percent of building inspections within three working days of the request. The Government aims to…

30 years on – Solicitor-General Prosecution Guidelines revamp

30 years on – What does the 2025 revamp of the Solicitor-General Prosecution Guidelines mean for local authorities? Overview The Solicitor-General Prosecution Guidelines are fundamental in shaping Aotearoa’s criminal justice system, and they have recently been updated following the most comprehensive review in over 30 years. While the definition of “prosecuting agency” excludes local authorities,…